Accelerated Housing Scheme-III

Sanctioned Construction of  6000 Residential Buildings under AHS-III scheme at a cost of Rs 440.00 Crores has beeen approved by GOK vide order no. HD/34/PBL/2007 dated 01.02.2008.  The number of quarters has been reduced to 4333 vide GO No. HD/43/PBL/2008  dt 04.11.08 due to increase in cost.








Details of  works under AHS-III  Scheme as on 30-04-2010
Sl. No. Details No. of Quarters Total No. of  Locations
PC SI Total
1  Handed over to user department 154 19 173 9
2  Work completed, not taken over by user department 390 37 427 23
3  Work in progress 1556 110 1666 84
4  LOA issued. Work to be started 126 4 130 7
5  Tender to be finalised 6   6 1
6  Tender under process 144 8 152 4
TOTAL 2376 178 2554 128